23 Novembre 2020
Achievements
course: home > Achievements

ENDECO KK PLC

TEXTILE , 100-500 MC/DAY , ETHIOPIA
YEAR OF INSTALLATION/INTERVENTION 2003

DELTACQUE typology of action
- Feasibility Study
- Pilot test
- Definitive and Executive project
- Machinery supply
- Assistance to the assembly
- Works supervision in the yard
- Plant start-up

Aims of the action
- Pre-treatment and treatment of the wastewater
- Biological treatment plant
- Biological sedimentation plant
- Sludge treatment plant
- Tertiary treatment plant
- Tertiary sedimentation plant

Plant capacity
- Hydraulic capacity of the plant: 400 m³/day

Waste Water features
Volume m³/day
Inlet: 400 Outlet: 400
C.O.D. mg/l
Inlet: 1.200 Outlet: 100
B.O.D. mg/l
Inlet: 720 Outlet: 60
pH
Inlet: 5-6 Outlet: 7-8